Conceptual & detailed design - Sea Tech,
2018-2023
Exterior design
- Sea Tech Studio
Chief
designers - P. Ezhov, A. Golov, A. Bondarenko
Consultants - S.Nikonov, S.Ayrapetov, G.Migeotte
Customer
- Severrechflot
Yard -
Zelenodolsk Shipyard (Rus), 2021-2023
Series - 4 vessels
(serial no.201-204)
Modern
high-speed passenger hydrofoil, project 03830 - representative of the
Alfa line
of hydrofoil
vessels (Alfa-120). Detailed design.
In 2018,
the Zelenodolsk Shipyard and the Sea Tech Ltd, based on
an analysis of the requests of operating organizations, many
years of research experience and modern technologies,
developed new requirements (technical conditions) for a
modern version of a passenger hydrofoil vessel.
During
the design process, the dimensions of the vessel, its
proportions, layout, engines, equipment, etc. were
repeatedly revised to achieve the optimal result in terms of
transport efficiency and comfort
for passengers and crew.
The project was developed in close dialogue with the
Customer.
The technical design was approved by the RRR (RKO) at the
beginning of 2021. This page contains demo materials of the
classification project stage.
2018-2020 - conceptual and classification stages of
the project.
2021-2022 - the detailed design stage.
03/02/2021- a solemn ceremony of laying 2 vessels was held at the Zelenodolsk Shipyard, which is part
of the Ak Bars Shipbuilding Corporation, for the
Khanty-Mansi Autonomous Okrug.
06/29/2022 -
launch of the lead vessel.
11/18/2022 - start of sea trials.
August
2023 - the lead and 3 vessels of the series were delivered
to customers. |
|
|